Saturday, January 26, 2008

Seats

We received word this week the seats are ready to be shipped. Here is a transcript of the email:

Hello Micheal These are pictures taken at the factory of a couple of your assembled chairs. Your order is ready to ship. Please email me your theatre address. Thanks Sam
Norton cinema order ready.
Below are some images of the chair samples, More pictures are enclosed for your reference.







Monday, January 21, 2008

Construction Update # 11 Part 2

Just a quick update on the status of our grand opening. We are shooting for a March 1st 2008 . It's possible we could be a week earlier or a week later. As you can see from the latest updates, we are nearing completion in terms of the movie houses. We need to hang the curtains, set the speakers and put down carpet. Then we will be ready for the seats. After that, the houses will be complete. So it's getting closer. We want to thank you for your patience and encourage you to check back often for updates!

Construction Update # 11

Notice the paint around the stadium structure. Next step is hanging the curtains.

View from the floor of the 1st movie house.


Another look at how impressive the movie house looks from floor level.

Notice the small movie houses have 3 surround speakers on each wall.

This week the trees on the bank along the new cinema are being cut down.


Another shot of the locust trees there were cut down on the bank.

Thursday, January 10, 2008

Construction Update # 10

Fresh concrete is being poured this week to all the stadium structures.

Closeup of the freshly poured concrete

Great looking shot of the entire stadium structure with the poured concrete.


This is a great shot contrasting the stadium structure that has the concrete poured.

This is the last movie house that is empty. Work will begin on installing the stadium seating structure and concrete pouring this week.

Drop ceiling being installed in the hallways.


The drop ceiling was installed in the bathroom this week.

The bathrooms are nearly done.


The hallway received a fresh coat of primer.


More equipment arrived this week; these boxes contain brand new projector equipment!


The rails leading up to the upstairs office were installed this week.