Sunday, December 23, 2007

Construction Update # 9

The stadium seating structure has been installed in two of the new cinemas!

Close up view of the steps along the wall of the new stadium seating structure.

Side angle view of the new stadium seating structure.

Floor level view of the new stadium seating structure.

Great shot looking from the top of the new stadium seating structure.

Close up shot of the styrofoam. A 4 inch concrete pad will be laid over this to form the floor.


This is a great look at the smallest movie house at the new cinema. The test screen is an old one that came from the Coeburn Cinema. As you can see, even the smallest movie house at the new cinema is 2-3 feet bigger than the old screens!


The four wooden blocks on the wall are speaker mounts. There will be 4 surround speakers on each side, 3 speakers in the front and 4 in the back.


This view is from the projector window above movie house 1

Sunday, December 16, 2007

Construction Update # 8

The new sign arrived from Jerrys this week. As you can see the end product differed from the initial concept. Still, we love the sign and it brings us one step closer to opening!

Another shot of our new sign.


We have a tremendous amount of gratitude to the City of Norton for replacing the sidewalk in front of the new cinema and repaving the road and entrance. Thank you Norton civic leaders!


Another shot of our new sidewalk and pavement. It's a relief to enter the shopping center parking lot now and not bottom our your car! Again, we can't heap enough praise onto the city of Norton and their public works department.


The outside is coming along nicely!

More painting is being done to the outside of the building


New concrete and new paint.....looking good!

Close up shot of the front with the new paint scheme.



Shot looking at the lobby...its coming along nicely too. Soon we will have the area to the left filled with new games! The order has been placed and the machines should be arriving in January.


Neat shot looking at the styrofoam inserts that will be placed in each movie house. After this has been done we will be ready to start on installing the seats.




Sunday, December 2, 2007

Construction Update # 7 Part 2

Just wanted to give everyone an update on time time frame as to when we should have our grand opening. It's still hard to put an exact date on it, but we hope sometime in January/February. You can see from the pictures things are coming along but at a much slower pace. When we get closer we will try to announce a firm date for our grand opening. Thanks and we look forward to seeing you!

Construction Update # 7


This week we unveil what we have affectionately dubbed "popcorn" tile behind the concessions. This area is located directly behind where you will stand in line while ordering your popcorn and snacks. Mike had the idea and it definitely gives off the idea of popcorn being popped from the kettle. We love it and hope you do too!

Another look at the "popcorn" tile.

Entrance to the party room

Closer look inside the party room

Work is being done to the exterior of the building.....a new paint job!

The outside of the building getting a fresh coat of paint


This sign is temporarily being taken down while the exterior of the building is being painted.

Behind the cinema is looking less and less like a set from the new Mad Max movie. When completed, this area will provide additional parking.


View of the 1st movie house from atop where the projector is. The next steps are installing the actual screen and seats. Getting closer!

Toilets are being installed in the mens bathroom

Tuesday, November 20, 2007

Construction Update # 6

Mike is testing paint schemes that will be used on the walls

Possible wall colors

Those can like objects on the wall are lights.

Those styrofoam blocks will be used in the construction of the stadium seating

Those wooden crates will house the center subwoofer and front surround speakers

This is the entrance to the party room

More new sound equipment awaiting installation.

Brand new sound equipment straight from JBL

These are lights that will showcase the concessions menu

A new small divider wall has been put up at the entrance to the cinema

Finished wall separating the cinema seats and entrance to the movie house.

Here is where you will stand in line at the concessions.


Tile has been laid in the bathrooms

Monday, October 22, 2007

Construction Update # 6

Brand new pieces of sound equipment arrived this week!

Neat looking shot at the completed duct work in the lobby area.


Duct work was completed this week

Great shot of the huge lobby area. Dry wall work is complete in this area.

The dry wall work is nearly complete. All that's left is this little section at the entrance.

This is a great shot showing the completed dry wall work in the lobby.


Freshly poured concrete outside the entrance to the new cinema

Work on the new fire escape and outside stairs

When finished this will be a fire escape from the upper level of the cinema

The new sign should arrive soon!

The city of Norton is fixing the streets along the entire shopping center. It will no longer be a car threating experience to enter the shopping center. A big thank you to the city of Norton!



Another look at the sidewalk that is being totally redone.